Water Treatment Project
Project Details

Mobile Sanitary Treatment Plant - 5,400 M3/Day.

  • Client
    Saudi Aramco
  • Engineering Consultant
    IE-Consult Office
  • Technical Partner
    MENA-Water
  • Technology
    Membrane Biological Reactor (MBR)
  • Date
    July 28,2016

Project Summery

In 2014, Saudi Aramco began constructing the Jazan Refinery Plant and Terminal in Baish. The facilities form the industrial heart of the government’s greater Jazan Economic City project (JEC). During the development and construction of this STP, a wastewater treatment innovated concept was required. The centralized wastewater treatment plant at JEC is designed to receive domestic wastewater through tanker trucks from Saudi Aramco contractors’ camps.

  • Consists of 1,250 M3/day Containerized MBR as building blocks for the final size required at any site.
  • Redesign the CSTR to PFR to use GRP Tanks to expedite the construction
  • Allows easy assembly & disassembly for mobility from one site to another.
  • It takes three weeks to build one block (1 unit) ready for operation.
FK & Partner Co. successfully invented a new design for building large scale Sanitary
Wastewater Treatment Plants within short period of time.